How to Inspect a New McCloskey Crusher, Screener, or Stacker: A 7-Step Checklist
-
Who This Checklist Is For
-
Step 1: Lock the Specs Down in Writing Before Anything Ships
-
Step 2: Do a Visual Inspection Before Unloading
-
Step 3: Verify Wear Parts and Accessories
-
Step 4: Check Serial Numbers, Nameplates, and Documentation
-
Step 5: Run an Empty Test
-
Step 6: Run a Loaded Test—and Check the Specs On-Site
-
Step 7: Run the TCO Numbers Before You Sign
-
Common Mistakes
Who This Checklist Is For
If you're taking delivery of a new McCloskey crusher, screener, or stacker—or you're evaluating one for a quarry, contracting outfit, or mining operation—this list is for you. It's seven practical steps. Each one came from an actual problem on a site, not a policy document.
I work as a quality and brand compliance manager at an equipment outfit. Four years now. Roughly 200 deliveries move through my desk each year, and in our Q1 2024 audit, I rejected about 12% of first deliveries for spec mismatches, missing documentation, or failed run tests. Here's the process I actually run each time.
Step 1: Lock the Specs Down in Writing Before Anything Ships
Most buyers check specs after the machine shows up. That's too late. The outsider blindspot here: buyers focus on the name on the machine and completely miss the specific jaw configuration and sizing on the spec sheet.
In 2023, we received a jaw crusher quoted at a 27-inch jaw opening. Measured at 25.8 inches—4mm off the nominal spec, where normal tolerance is ±2mm. The vendor claimed it was "within industry standard." We rejected the batch, and they redid it at their cost. Now every PO includes a spec confirmation sheet signed by both sides.
Whether you're buying from McCloskey of St. Louis or any other regional dealer, get jaw settings, open-side dimensions, screen mesh type, deck count, and belt speeds confirmed on the order acknowledgment. Don't accept "standard specs" on a PO. Don't accept "same as last time" unless you've pulled up last time's written specs.
Step 2: Do a Visual Inspection Before Unloading
Do this the moment the flatbed pulls into your yard. Photograph the tie-downs, seals, and visible condition. If the machine is on a trailer, check the trailer locks and emergency brake before you release the tie-downs.
Our logistics lead, Amanda, once had to dispatch a pickup truck to grab a set of deck panels that had come loose because nobody double-checked the tie-downs after the loading crew moved a strap. That one cost us $1,200 and two days of production—just for skipping a five-minute check.
I'm not going to pretend this is rocket science. They warned me to check every delivery. I didn't listen once. That's reverse validation for you: one $1,200 lesson taught me more than four years of paperwork ever did.
Step 3: Verify Wear Parts and Accessories
Jaw plates, screen meshes, liners, side discharge belts, bypass chutes. These are expensive to replace and frequently short-shipped. Compare against the packing list. Count the fasteners, tensioners, and shims—small parts are the #1 target for theft and loss.
If something's missing, ask for it before you sign the receiving slip. Once you sign, you've accepted it.
Step 4: Check Serial Numbers, Nameplates, and Documentation
The serial number must match the invoice, the documents that came with the delivery, and the warranty registration. Check CE/UKCA labels (if applicable), machine tags, and warranty registration forms. Mismatched paperwork is a massive red flag for later warranty claims.
See if you can get a written acknowledgment from the vendor. Our hardest warranty claim was a mismatch on the serial number. The dealer suspected us, we suspected the dealer, and it took six months to resolve.
Step 5: Run an Empty Test
Before any material goes in, run the machine empty for 15-20 minutes. Check hydraulic functions, belt tracking, bearing temperatures, and unusual vibration. If you hear a rhythmic rub or knock, that's not normal.
Here's the part most people skip: empty noise doesn't necessarily match loaded noise. But problems usually show up empty first. Skip this and you'll pay for the problem loaded.
Step 6: Run a Loaded Test—and Check the Specs On-Site
Now load real material. Check throughput, product gradation, and screen efficiency. Measure the jaw setting and throughput against the specs you confirmed in Step 1. If the spec doesn't match, stop immediately. Don't accept "it'll settle in" as an answer.
If you're choosing between a machine with a jaw setting that's off and a hydraulic response that lags, experience tells me: reject both. Ask for a replacement.
Step 7: Run the TCO Numbers Before You Sign
This is where I live, professionally. Most buyers focus on cost per ton and completely miss fuel efficiency, wear-part lifespan, downtime risk, and service response time. In most of my purchasing decisions, the lowest initial quote has cost us more over five years.
Everything I'd read about equipment procurement said to compare per-unit pricing. In practice, the TCO comparison is what actually protects you. Here's a quick check:
- Five-year wear-part replacement cost
- Estimated downtime loss (hourly output × downtime hours per year)
- Service response time and risk factor
- Resale value after five years
We compared a low-cost domestic screener against a McCloskey model back in 2022. Base quote was $22,000 apart. But the low-cost unit needed twice the wear parts and had worse downtime. Verdict: the McCloskey was about $18,000 ahead over five years.
If the numbers don't line up, don't sign. A $200 savings turned into a $1,500 problem when we ignored that step once. I've run the math on 200+ orders, and I'm fairly convinced the pattern holds more or less every time.
Common Mistakes
These are the ones I see most—including on my own watch:
- Skipping the written spec in Step 1—don't accept "standard specs."
- Signing before a run test—absolutely not.
- Ignoring wear parts and hidden costs—calculate TCO, not sticker price.
- Assuming the dealer handled the paperwork—you verify it.
- Forgetting serial-number tracking and warranty registration.
My take: in crusher and screener purchasing, the most valuable step is always Step 1—get the specs in writing before anything unloads. It isn't theory. It's experience. It works, every time.