Insight Article / compact

McLanahan Crushed Stone Equipment: What to Expect for Budgeting and Maintenance

2026-05-28

If you're looking into McLanahan crushed stone equipment, you're probably trying to figure out if it's the right fit for your operation. And if you're anything like me (procurement manager for a mid-sized aggregate company), you're also trying to figure out what it's actually going to cost you over the long haul.

Let's be upfront: there's no single answer. Your decision depends heavily on your specific operation, your feed material, and your production goals. I've been tracking our equipment costs for the past 6 years, and I've seen this play out in a few different ways depending on the situation.

Scenario A: You're Setting Up a New Greenfield Site

This is the most straightforward scenario in some ways, because you're working with a clean slate. You have the opportunity to design your circuit from the ground up, which is rare and valuable.

Here's what I've learned from evaluating vendors for a new site in 2023. We compared quotes from 4 manufacturers for a complete crushing and screening circuit. McLanahan was competitive on the crushers and screening equipment, but their real strength showed up in the washing and classifying stages.

For budgeting purposes, here's what you should expect:

  • Primary jaw crusher: Expect to budget around $250,000-$400,000 depending on capacity (pricing from vendor quotes, Q1 2024).
  • Cone crushers: $150,000-$300,000 each for mid-range units.
  • Washing systems (if needed): This is where McLanahan's expertise shines. A complete sand and gravel wash plant can run $500,000-$1.5 million.

One thing I didn't anticipate: the lead times. When we ordered our primary crusher in early 2023, the timeline was 16-20 weeks. That's not unusual for heavy equipment, but it's worth factoring into your project schedule. We had to push back our site commissioning by about a month because we didn't account for that.

Oh, and I should mention: McLanahan often includes a site visit for new installations in their quote. That's fairly standard for major equipment manufacturers, but it's worth confirming. It saved us some headaches around foundation design.

Scenario B: You're Replacing a Worn-Out Unit

This is a different animal entirely. If you're replacing a crusher or screen that's reached the end of its life, you're working within an existing circuit, which means compatibility matters.

I've been through this twice now. The first time, in 2021, we replaced a jaw crusher that had been in service for 15 years. The new unit had slightly different dimensions, and we ended up spending about $8,000 on modifications to the existing feed chute and discharge conveyor. That was a lesson in measuring twice, ordering once.

For replacement scenarios, here's my process:

  1. Get exact dimensions of your existing mounting points before you even start talking to vendors. We learned this the hard way.
  2. Ask about retrofit kits. McLanahan seems to offer retrofit packages for some of their more popular models, which can save you significant modification costs.
  3. Factor in the downtime. When we replaced a screen deck in Q2 2024, the actual removal and installation took 3 days. But we'd scheduled 5 because we expected the unexpected. Smart move, as it turned out—we had a minor bearing issue that added a day.

As of late 2024, a replacement cone crusher from McLanahan was running about $180,000-$350,000 depending on model and configuration. That's based on a quote we received in October 2024. Prices may have changed since then.

Scenario C: You're Expanding Capacity

This is probably the most common scenario I see in our industry. You need to increase throughput, but you're not starting from scratch. Maybe you're adding a secondary crusher, or a new screen deck, or a washing module.

What most people don't realize is that adding equipment to an existing circuit isn't just about the machine itself. The bottlenecks are often in the auxiliary systems—conveyors, chutes, electrical. I made this mistake in my first year: I costed out the crusher itself but didn't budget for the conveyor upgrades and electrical work. Cost me about $15,000 in unplanned expenses.

Here's something vendors won't tell you: the first quote is almost never the final price for ongoing relationships. We've been working with McLanahan for about 4 years now, and our later quotes were 8-12% less than the initial ones. Not because of any special deal—we just had a better understanding of what we needed and could communicate more clearly.

For expansion projects, budget roughly 15-20% above the equipment cost for installation and integration. That's been my experience across 3 expansion projects at our plant. I don't have hard data on industry-wide numbers, but based on our 6 years of tracking, that's a reasonable figure.

How to Tell Which Scenario Applies to You

This might sound obvious, but I see a lot of procurement mistakes happen when people treat one scenario like another. Here's how to figure out where you stand:

  • Are you building from scratch? You're in Scenario A. Focus on total circuit design, not just individual machine specs.
  • Is your existing equipment at 80%+ of its expected life? You're likely in Scenario B. Start measuring and planning now—waiting until it fails will cost you in downtime.
  • Are you seeing capacity constraints in specific areas of your circuit? You're in Scenario C. Identify your bottlenecks before you buy anything.

I built a simple cost calculator after getting burned on hidden fees twice. It factors in installation, modifications, electrical, and contingency. If you want a copy, I can share a template—just keep in mind it's based on our operation in the Southeast US, so things like labor rates will vary.

The fundamentals of equipment procurement haven't changed much in the past decade: understand your needs, get multiple quotes, and budget for the unexpected. But the execution—the specifics of how you manage that process—has transformed with better data and communication tools. What was best practice in 2020 may not apply in 2025.

Pricing is for general reference only, based on vendor quotes from Q1-Q4 2024. Actual prices vary by configuration, region, and market conditions. Always verify current pricing directly with McLanahan or your local dealer.

Previous: I Almost Cost My Company $2,400 (and What It Taught Me About Verifying Every Order Detail)
Next: I Paid $400 in Rush Fees Because of a Moth. Here's What I Learned About Print Deadlines.